Tune
for cleanup of U-233 changes
Nuke
material to be disposed of, and cost to do so has nearly tripled to $379M
By
FRANK MUNGER, December 11, 2006
OAK
RIDGE - The U.S. Department of Energy has revised its strategy - and its price
tag - for one of the most challenging nuclear projects in recent history.
The
government's goal is to get rid of a large stockpile of uranium-233 stored in
a World War II-era building at Oak Ridge National Laboratory.
The
Oak Ridge project is fraught with risk, both from a safety and a security standpoint.
The uranium-233 is a strategic nuclear material of potential use in nuclear bombs,
thus requiring the highest level of security. It also is hotly radioactive because
of byproducts formed during its decay - such as thorium-229 - and some work must
be performed remotely to protect workers.
The
newly estimated cost is $379.2 million, according to Steve McCracken, the environmental
cleanup chief in Oak Ridge. That's almost triple the $128 million DOE announced
when awarding a contract for the project in 2003.
But
McCracken said the original figure did not cover all aspects of the work, such
as the cost for shipping containers, associated work at another nuclear facility,
long-term storage of materials and about $70 million included for "risks
and uncertainties."
The
actual cost growth was from about $250 million to the current level, he said.
The
nuclear stockpile has been in storage at ORNL since the 1960s. It is a legacy
of experiments conducted under the auspices of the Atomic Energy Commission, a
federal predecessor to DOE, which was interested in using U-233 as a fuel for
nuclear reactors.
"Obviously
they need to deal with the material. They should have dealt with it long ago,"
said Susan Gawarecki, executive director of the Local Oversight Committee, which
evaluates environmental issues for local governments in the Oak Ridge area.
The
project was altered this year after Congress instructed DOE, as part of a 2006
appropriations bill, to scrap plans to extract medical isotopes from the nuclear
stockpile. So DOE is moving forward with disposition of the material, even though
critics say that radioisotopes could be used in life-saving cancer treatments.
Oak
Ridge officials issued a revised environmental assessment Dec. 6 and said they
would accept public comment through Dec. 22. That's a relatively short comment
period, but DOE said it's sufficient because the potential impacts are still pretty
much the same as in an earlier review.
The
plan, in general, is to modify the existing storage facility - Building 3019-A
at ORNL - and install equipment needed to process the U-233 to eliminate its weapons
capability and to prepare it for disposal.
That
will be accomplished by "down-blending" the U-233 with stocks of depleted
uranium, which have most of the fissile isotopes already removed.
According
to the draft report, DOE intends to acquire the necessary depleted uranium from
the agency's Savannah River Site in South Carolina. Even though tons of depleted
uranium are stored in Oak Ridge, none of it was deemed suitable for this particular
project, the report said.
About
225,000 kilograms of depleted uranium will be shipped from Savannah River to the
Nuclear Fuel Services plant at Erwin, Tenn. It will be processed and converted
to uranyl nitrate, a chemical form needed for the next step, and transported to
Oak Ridge.
The
down-blending is expected to begin in July 2012, with project completion scheduled
for 2016, said Walter Perry, a DOE spokesman.
Isotek
Systems Inc., a partnership involving EnergySolutions, Burns and Roe, and Nuclear
Fuel Services, is the contractor on the project.
Once
the enriched uranium is down-blended and converted to an oxide form, it will be
removed from Building 3019-A, a 63-year-old structure that critics have said is
vulnerable to terrorism. The repackaged materials will be stored at a site in
Melton Valley west of ORNL until a disposal site is approved.
Lance
Mezga, a geologist who heads a citizens board that advises DOE on environmental
matters, said he's confident the technical expertise is available to do the job
safely. The advisory board, however, continues to raise questions about the ultimate
disposition of the material, he said.
"We
don't want to continue storing these materials on site for a lot of reasons,"
Mezga said.
John
Owsley, the state's environmental oversight site chief, said it's possible the
radioactive waste could be shipped to the Waste Isolation Pilot Plant in New Mexico
or the Nevada Test Site for disposal.
The
inventory of U-233 is contained in about 1,200 canisters, which are housed in
shielded tube vaults inside the ORNL building, DOE said. An earlier risk assessment
indicated the containers were in pretty good shape, although minor corrosion has
taken place, the report said.
After
the down-blending work is completed, Building 3019-A will be decommissioned. That,
too, could be a hazardous adventure.
The
building once housed operations that chemically processed fuel from the nearby
Graphite Reactor. In 1959, a chemical explosion "distributed plutonium contamination
throughout the interior and exterior of the building." Although a cleanup
project was done at the time, radioactive particles remained behind, and workers
painted the walls to prevent the spread of contamination.
In
addition to the radioactive hazards, Building 3019-A has uncoated lead shielding,
lead paint, polychlorinated biphenyls, asbestos and other hazards. There also
is an "underground ventilated bunker" that contains about 4,000 gallons
of thorium nitrate solution that's contaminated with U-233.